A gentle warm mid-autumn day was the backdrop for MPEC's celebration of completion of the first phase of the Horseshoe Lodge Project. An estimated 300 people showed up to celebrate, enjoy some delicious goodies, tour the Lodge, and learn a bit about what comes next for MPEC at Horseshoe Lodge. Words of wisdom, story and insight were shared by Pueblo City Councilman Randy Thurston, MPEC Board Member Anne Warren and her son, MPEC camper Zach Warren, camper Jackson Reed, founding MPEC Board Member
Tim Sandsmark (now Director of Lookout Mountain Nature Center in Jefferson County), Pueblo County Commissioner Jeff Chostner, and MPEC Founder and Director Dave Van Manen. A surprise visit by Dudley McFarland, a CCC worker who worked in Pueblo Mountain Park in 1935 (he's now 95) and a donation by the National Automobile Sales Association presented by Barbara and Bill Vidmar added to the day's delight. A few youngsters from our Nature Toddlers group cut the ribbon that officially opened the Horseshoe Lodge as MPEC's new home. The day was both a celebration of the completion of Phase 1 and a kick-off of fund-raising for the remaining phases of the exciting Horseshoe Lodge Project - which we
already have quite a bit of the necessary funds to get Phase 2 - the overnight rooms in the west wing - started and completed! Click the ribbon-cutting photo on the right to see lots of Grand Opening photos.
10/20/2008
10/13/2008
10/01/2008
October color in Pueblo Mountain Park!
October arrives with lots of color - from many flowers still in bloom and leaves as colorful as flowers in their autumn look. I finally have another camera (thank you, Helene) and have stolen a few moments to try it out. Here is some of what Pueblo Mountain Park has to offer these soft autumn days: Lots of members of the Sunflower Family, and, yes, that is poison ivy (the Sumac Family). The deer are very plentiful - I saw this one walking home from the office yesterday evening around 6pm right at the entrance to the park.
8/20/2008
7/30/2008
In the Last 3 Weeks This Has Happened At The Mountain Park Environmental Center
At the Horseshoe Lodge we have:
- Painted about 10,000 sq feet of walls and ceilings x 3 coats
all by volunteers
-Tongue in groove ceiling is almost completely installed
-Bathrooms are primed for completion and will feature Clivus Multrum foam flush composting toilets
-Electrical finish work is near completion
-Floors are being repaired where needed and old baseboard removed last winter are being sanded and restored by a volunteer and will be installed in the next week or two
-New phone systems are ready to be installed
-New Interior doors will arrive August 6th
We plan to move from our overcrowded MPEC headquarters to the new Horseshoe Lodge on Saturday August 23. We are rallying volunteers to help us move that day and celebrate this huge grassroots effort. We need helpers at every level including people to cook and bring food to feed our moving troops. email us at I WILL HELP MPEC MOVE
- Painted about 10,000 sq feet of walls and ceilings x 3 coats
all by volunteers
-Tongue in groove ceiling is almost completely installed
-Bathrooms are primed for completion and will feature Clivus Multrum foam flush composting toilets
-Electrical finish work is near completion
-Floors are being repaired where needed and old baseboard removed last winter are being sanded and restored by a volunteer and will be installed in the next week or two
-New phone systems are ready to be installed
-New Interior doors will arrive August 6th
We plan to move from our overcrowded MPEC headquarters to the new Horseshoe Lodge on Saturday August 23. We are rallying volunteers to help us move that day and celebrate this huge grassroots effort. We need helpers at every level including people to cook and bring food to feed our moving troops. email us at I WILL HELP MPEC MOVE